Build Updates
Check out this month’s build updates below.
Last updated 01/12/2021

21-23 Titoki Street
Te Atatu Peninsula
Work Completed Last Month:
- Internal Painting
- Cladding
Work Planned This Month:
- Landscaping
- Kitchen
- Internal Fit Off
Estimated Settlement Date: January 2022
14 Townhouses

34 Sunnymead Road
Glen Innes
Work Completed Last Month:
- Internal Painting
- Cladding
- Concrete Paths
- Kitchen
- Internal Fit Off
Work Planned This Month:
- Landscaping
Estimated Settlement Date: January 2022
10 Townhouses

32 Sunnymead Road
Glen Innes
Work Completed Last Month:
- GIB Fix & Stop
- Internal Painting
- Kitchen
Work Planned This Month:
- Cladding
- Landscaping
- Internal Fit Off
Estimated Settlement Date: January 2022
10 Townhouses


57 Taikata Road
Te Atatu Peninsula
Work Completed Last Month:
- Cladding
- Concrete Paths
Work Planned This Month:
- Landscaping
Estimated Settlement Date: February 2022
10 Townhouses

79 Taikata Road
Te Atatu Peninsula
Work Completed Last Month:
- Internal Painting
- Cladding
- Kitchen
- Internal Fit Off
Work Planned This Month:
- Landscaping
- Concrete Paths
Estimated Settlement Date: January 2022
11 Townhouses


137 View Road
Sunnyvale
Work Completed Last Month:
- Windows
- Exterior Wrap
Work Planned This Month:
- GIB Fix & Stop
- Internal Painting
- Cladding
Estimated Settlement Date: January 2022
8 Townhouses


59 Neil Avenue
Te Atatu Peninsula
Work Completed Last Month:
- GIB Fix & Stop
Work Planned This Month:
- Internal Painting
- Cladding
- Landscaping
- Kitchen
- Internal Fit Off
Estimated Settlement Date: January 2022
11 Townhouses

40-42 Kaikoura Street
Henderson
Work Completed Last Month:
- Cladding
- Concrete Paths
- Carparks
- Kitchen
- Internal Fit Off
Work Planned This Month:
- Landscaping
Estimated Settlement Date: January 2022
15 Townhouses

10-12 Wilsher Crescent
Henderson
Work Completed Last Month:
- GIB Fix & Stop
- Internal Painting
Work Planned This Month:
- Cladding
- Landscaping
- Internal Fit Off
Estimated Settlement Date: January 2022
14 Townhouses

14 Wilsher Crescent
Henderson
Work Completed Last Month:
- Windows
- Concrete Paths
Work Planned This Month:
- GIB Fix & Stop
- Internal Painting
- Cladding
- Landscaping
- Carparks
- Kitchen
- Internal Fit Off
Estimated Settlement Date: January 2022
8 Townhouses

10 Yeovil Road
Te Atatu Peninsula
Work Completed Last Month:
- GIB Fix & Stop
Work Planned This Month:
- Internal Painting
- Cladding
Estimated Settlement Date: March 2022
11 Townhouses

81 Kervil Avenue
Te Atatu Peninsula
Work Completed Last Month:
- Roof
- Windows
- Exterior Wrap
Work Planned This Month:
- GIB Fix & Stop
- Internal Painting
- Cladding
Estimated Settlement Date: March 2022
11 Townhouses

24 Yeovil Road
Te Atatu Peninsula
Work Completed Last Month:
- Roof
- Windows
Work Planned This Month:
- Drains
- GIB Fix & Stop
- Internal Painting
- Cladding
Estimated Settlement Date: March 2022
11 Townhouses


19 Karamu Street
Te Atatu Peninsula
Work Completed Last Month:
- Roof
- Windows
- Exterior Wrap
Work Planned This Month:
- GIB Fix & Stop
- Internal Painting
- Cladding
Estimated Settlement Date: March 2022
11 Townhouses

22 Yeovil Road
Te Atatu Peninsula
Work Completed Last Month:
- Roof
- Exterior Wrap
Work Planned This Month:
- Drains
- Windows
- GIB Fix & Stop
- Cladding
Estimated Settlement Date: March 2022
11 Townhouses


137 Tirimoana Road
Te Atatu South
Work Completed Last Month:
- Drains
- Frame & Truss
- Roof
- Windows
Work Planned This Month:
- Exterior Wrap
- GIB Fix & Stop
- Carparks
Estimated Settlement Date: March 2022
11 Townhouses


10 Willcott Street
Mt Albert
Work Completed Last Month:
- Excavation
- Slab
Work Planned This Month:
- Drains
- Frame & Truss
Estimated Settlement Date: March 2022
13 Townhouses


87 Taikata Road
Te Atatu Peninsula
Work Completed Last Month:
- Excavation
- Drains
Work Planned This Month:
- Slab
- Frame & Truss
Estimated Settlement Date: May 2022
10 Townhouses

59-61 Matipo Road
Te Atatu Peninsula
Work Completed Last Month:
- Planning & Consenting
- Site Clearance
Work Planned This Month:
- Planning & Consenting Continued
Estimated Settlement Date: May 2022
22 Townhouses

200 Carrington Road
Mt Albert
Work Completed Last Month:
- Planning & Consenting
- Site Clearance
Work Planned This Month:
- Planning & Consenting Continued
- Excavation
Estimated Settlement Date: August 2022
34 Townhouses

49 Te Kanawa Crescent
Henderson
Work Completed Last Month:
- Planning & Consenting
Work Planned This Month:
- Planning & Consenting Continued
Estimated Settlement Date: September 2022
28 Townhouses

59 Wingate Street
Avondale
Work Completed Last Month:
- Planning & Consenting
Work Planned This Month:
- Planning & Consenting Continued
Estimated Settlement Date: September 2022
15 Townhouses

170 Don Buck Road
Massey
Work Completed Last Month:
- Planning & Consenting
Work Planned This Month:
- Planning & Consenting Continued
Estimated Settlement Date: September 2022
22 Townhouses

Got a Question?
Christchurch Build Updates

35-41 Chester Street West
Central Christchurch
Work Completed Last Month:
- Cladding
- Landscaping
- Internal Fit Off
Work Planned This Month:
- Internal Fit Off
Estimated Settlement Date: December 2021
15 Townhouses

320 Hereford Street
Central Christchurch
Work Completed Last Month:
- GIB Fix & Stop
- Cladding
Work Planned This Month:
- Internal Painting
- Landscaping
- Concrete Paths
- Kitchen
- Internal Fit Off
Estimated Settlement Date: December 2021
14 Townhouses

483-487 Selwyn Street
Central Christchurch
Work Completed Last Month:
- Windows
- Exterior Wrap
- GIB Fix & Stop
- Concrete Paths
Work Planned This Month:
- Internal Painting
- Cladding
- Landscaping
- Kitchen
- Internal Fit Off
Estimated Settlement Date: December 2021
13 Townhouses

28 Aberdeen & 365 Madras Street
Central Christchurch
Work Completed Last Month:
- Frame & Truss
- Roof
Work Planned This Month:
- Frame & Truss
- Roof
- Windows
Estimated Settlement Date: March 2022
44 Townhouses

237 Lichfield Street
Central Christchurch
Work Completed Last Month:
- Drains
Work Planned This Month:
- Frame & Truss
- Roof
- Windows
Estimated Settlement Date: April 2022
19 Townhouses

322 Durham Street
Central Christchurch
Work Completed Last Month:
- Slab
- Drains
Work Planned This Month:
- Frame & Truss
- Roof
Estimated Settlement Date: May 2022
18 Townhouses

96 Tuam St
Central Christchurch
Work Completed Last Month:
- Planning & Consenting
- Excavation
Work Planned This Month:
- Slab
Estimated Settlement Date: June 2022
26 Townhouses

169-171 St Asaph Street
Central Christchurch
Work Completed Last Month:
- Planning & Consenting
- Excavation
- Slab
Work Planned This Month:
- Slab
- Drains
Estimated Settlement Date: June 2022
16 Townhouses

338 Cashel Street
Central Christchurch
Work Completed Last Month:
- Site Clearance
Work Planned This Month:
- Excavation
- Slab
Estimated Settlement Date: June 2022
19 Townhouses

9 Spencer Street
Addington
Work Completed Last Month:
- Planning & Consenting
Work Planned This Month:
- Site Clearance
Estimated Settlement Date: July 2022
16 Townhouses

210 Lincoln Road
Addington
Work Completed Last Month:
- Planning & Consenting
Work Planned This Month:
- Planning & Consenting Continued
- Site Clearance
- Excavation
Estimated Settlement Date: July 2022
25 Townhouses

835 Colombo Street
Central Christchurch
Work Completed Last Month:
- Excavation
Work Planned This Month:
- Planning & Consenting Continued
Estimated Settlement Date: August 2022
12 Townhouses

332 Cashel Street
Central Christchurch
Work Completed Last Month:
- Planning & Consenting
Work Planned This Month:
- Planning & Consenting Continued
Estimated Settlement Date: August 2022
19 Townhouses

52 Stewart Street
Central Christchurch
Work Completed Last Month:
- Planning & Consenting
Work Planned This Month:
- Planning & Consenting Continued
Estimated Settlement Date: September 2022
35 Townhouses

240 St Asaph Street & 15 Southwark Street
Central Christchurch
Work Completed Last Month:
- Planning & Consenting
Work Planned This Month:
- Planning & Consenting Continued
Estimated Settlement Date: September 2022
27 Townhouses

66b Wharenui Road
Upper Riccarton
Work Completed Last Month:
- Planning & Consenting
Work Planned This Month:
- Planning & Consenting Continued
- Site Clearance
Estimated Settlement Date: November 2022
82 Townhouses

76 Banks Ave
Dallington
Work Completed Last Month:
- Planning & Consenting
Work Planned This Month:
- Planning & Consenting Continued
Estimated Settlement Date: December 2022
49 Townhouses

Got a Question?
Wellington Build Updates

123 Cambridge Terrace
Lower Hutt
Work Completed Last Month:
- Landscaping
- Concrete Paths
- Carparks
- Kitchen
Work Planned This Month:
- Internal Fit Off
Estimated Settlement Date: December 2021
11 Townhouses

318-324 Oxford Terrace
Lower Hutt
Work Completed Last Month:
- Internal Painting
- Cladding
Work Planned This Month:
- Landscaping
- Concrete Paths
- Carparks
- Kitchen
- Internal Fit Off
Estimated Settlement Date: January 2022
28 Townhouses

4 Collingwood Street
Lower Hutt
Work Completed Last Month:
- Internal Painting
- Cladding
- Landscaping
- Kitchen
Work Planned This Month:
- Landscaping
- Internal Fit Off
Estimated Settlement Date: January 2022
11 Townhouses


14 Bauchop Road
Lower Hutt
Work Completed Last Month:
- GIB Fix & Stop
- Internal Painting
Work Planned This Month:
- Cladding
- Landscaping
- Concrete Paths
- Kitchen
- Internal Fit Off
Estimated Settlement Date: January 2022
13 Townhouses

148 Riverside Drive
Lower Hutt
Work Completed Last Month:
- Roof
- Windows
- Exterior Wrap
Work Planned This Month:
- GIB Fix & Stop
- Internal Painting
- Cladding
- Landscaping
- Kitchen
- Internal Fit Off
Estimated Settlement Date: January 2022
11 Townhouses

10 Avery Grove
Lower Hutt
Work Completed Last Month:
- GIB Fix & Stop
- Internal Painting
Work Planned This Month:
- Cladding
- Landscaping
- Concrete Paths
- Kitchen
- Internal Fit Off
Estimated Settlement Date: February 2022
14 Townhouses

11 Cressy Street
Lower Hutt
Work Completed Last Month:
- Cladding
Work Planned This Month:
- Internal Painting
- Landscaping
- Kitchen
- Internal Fit Off
Estimated Settlement Date: February 2022
8 Townhouses

17-19 Pearce Crescent
Lower Hutt
Work Completed Last Month:
- Frame & Truss
- Roof
- Windows
- Exterior Wrap
Work Planned This Month:
- GIB Fix & Stop
- Internal Painting
- Cladding
- Landscaping
- Concrete Paths
- Kitchen
- Internal Fit Off
Estimated Settlement Date: March 2022
12 Townhouses

182-183 Cambridge Terrace
Lower Hutt
Work Completed Last Month:
- Drains
- Frame & Truss
- Roof
- Windows
Work Planned This Month:
- Exterior Wrap
- GIB Fix & Stop
- Internal Painting
- Cladding
Estimated Settlement Date: May 2022
14 Townhouses

10-16 Biddle Crescent
Lower Hutt
Work Completed Last Month:
- Slab
- Drains
Work Planned This Month:
- Frame & Truss
- Roof
- Windows
- Exterior Wrap
- GIB Fix & Stop
Estimated Settlement Date: May 2022
30 Townhouses

5-7 Milne Crescent
Lower Hutt
Work Completed Last Month:
- Drains
Work Planned This Month:
- Frame & Truss
- Roof
- Windows
- Exterior Wrap
- GIB Fix & Stop
Estimated Settlement Date: June 2022
16 Townhouses

1 Milne Crescent
Lower Hutt
Work Completed Last Month:
- Slab
- Drains
Work Planned This Month:
- Frame & Truss
- Roof
- Windows
- Exterior Wrap
Estimated Settlement Date: June 2022
17 Townhouses

39 Merton Street
Upper Hutt
Work Completed Last Month:
- Planning & Consenting
Work Planned This Month:
- Planning & Consenting Continued
- Site Clearance
- Excavation
Estimated Settlement Date: June 2022
18 Townhouses

5-11 Macky Street
Lower Hutt
Work Completed Last Month:
- Planning & Consenting
- Site Clearance
- Excavation
- Slab
- Drains
Work Planned This Month:
- Frame & Truss
- Roof
- Windows
- Exterior Wrap
Estimated Settlement Date: July 2022
24 Townhouses

4 Johnston Grove
Lower Hutt
Work Completed Last Month:
- Excavation
Work Planned This Month:
- Slab
- Drains
- Frame & Truss
Estimated Settlement Date: July 2022
19 Townhouses

41 Collingwood Street
Lower Hutt
Work Completed Last Month:
- Planning & Consenting
Work Planned This Month:
- Site Clearance
- Excavation
Estimated Settlement Date: September 2022
12 Townhouses

14 Rainey Grove
Taita
Work Completed Last Month:
- Planning & Consenting
Work Planned This Month:
- Planning & Consenting Continued
Estimated Settlement Date: October 2022
35 Townhouses

Talk to Us
Whether you’re a first time home buyer, investor or someone that’s interested in growing their portfolio, we have properties available now.
Tauranga Build Updates

1204 Cameron Road
Gate Pa
Work Completed Last Month:
- Planning & Consenting
Work Planned This Month:
- Planning & Consenting Continued
Estimated Settlement Date: November 2022
18 Townhouses