Build Updates

Check out this month’s build updates below.

Last updated 01/10/2021

Auckland
Christchurch
Wellington
Talk to Us

Auckland Build Updates

41 Kervil Avenue

Te Atatu Peninsula

Work Completed Last Month:

  • Landscaping
  • Concrete Paths

Work Planned This Month:

  • Kitchen
  • Internal Fit Off

Estimated Settlement Date: December 2021

11 Townhouses

21-23 Titoki Street

Te Atatu Peninsula

Work Completed Last Month:

  • Slab
  • GIB Fix & Stop
  • Internal Painting
  • Concrete Paths
  • Carparks

Work Planned This Month:

  • Cladding
  • Landscaping
  • Kitchen
  • Internal Fit Off

Estimated Settlement Date: December 2021

14 Townhouses

32 Sunnymead Road

Glen Innes

Work Completed Last Month:

  • Roof
  • Windows
  • Exterior Wrap
  • Concrete Paths

Work Planned This Month:

  • GIB Fix & Stop
  • Internal Painting
  • Cladding
  • Landscaping
  • Kitchen
  • Internal Fit Off

Estimated Settlement Date: December 2021

10 Townhouses

34 Sunnymead Road

Glen Innes

Work Completed Last Month:

  • Roof
  • Windows
  • GIB Fix & Stop
  • Concrete Paths

Work Planned This Month:

  • Internal Painting
  • Cladding
  • Kitchen
  • Internal Fit Off

Estimated Settlement Date: January 2022

10 Townhouses

79 Taikata Road

Te Atatu Peninsula

Work Completed Last Month:

  • GIB Fix & Stop
  • Internal Painting

Work Planned This Month:

  • Cladding
  • Landscaping
  • Kitchen
  • Internal Fit Off

Estimated Settlement Date: January 2022

11 Townhouses

57 Taikata Road

Te Atatu Peninsula

Work Completed Last Month:

  • Internal Painting
  • Concrete Paths

Work Planned This Month:

  • Cladding
  • Landscaping
  • Concrete Paths
  • Kitchen

Estimated Settlement Date: January 2022

10 Townhouses

137 View Road

Sunnyvale

Work Completed Last Month:

  • Frame & Truss
  • Roof

Work Planned This Month:

  • Windows
  • Exterior Wrap
  • GIB Fix & Stop
  • Cladding

Estimated Settlement Date: January 2022

8 Townhouses

59 Neil Avenue

Te Atatu Peninsula

Work Completed Last Month:

  • Roof
  • Windows
  • Concrete Paths

Work Planned This Month:

  • GIB Fix & Stop
  • Internal Painting
  • Cladding

Estimated Settlement Date: January 2022

11 Townhouses

40-42 Kaikoura Street

Henderson

Work Completed Last Month:

  • Windows
  • Exterior Wrap
  • GIB Fix & Stop
  • Cladding
  • Concrete Paths
  • Carparks

Work Planned This Month:

  • Internal Painting
  • Kitchen
  • Internal Fit Off

Estimated Settlement Date: January 2022

15 Townhouses

10-12 Wilsher Crescent

Henderson

Work Completed Last Month:

  • Planning & Consenting
  • Site Clearance
  • Excavation
  • Slab
  • Drains
  • Frame & Truss

Work Planned This Month:

  • Roof
  • Windows
  • Exterior Wrap
  • GIB Fix & Stop
  • Internal Painting
  • Cladding

Estimated Settlement Date: January 2022

14 Townhouses

10 Yeovil Road

Te Atatu Peninsula

Work Completed Last Month:

  • Roof
  • Windows
  • Exterior Wrap

Work Planned This Month:

  • GIB Fix & Stop
  • Internal Painting
  • Cladding
  • Concrete Paths

Estimated Settlement Date: February 2022

11 Townhouses

14 Wilsher Crescent

Henderson

Work Completed Last Month:

  • Planning & Consenting
  • Site Clearance
  • Excavation
  • Slab
  • Drains
  • Frame & Truss

Work Planned This Month:

  • Roof
  • Windows
  • Exterior Wrap
  • GIB Fix & Stop
  • Internal Painting
  • Cladding
  • Concrete Paths

Estimated Settlement Date: February 2022

8 Townhouses

81 Kervil Avenue

Te Atatu Peninsula

Work Completed Last Month:

  • Frame & Truss
  • Concrete Paths

Work Planned This Month:

  • Roof
  • Windows
  • Exterior Wrap

Estimated Settlement Date: February 2022

11 Townhouses

24 Yeovil Road

Te Atatu Peninsula

Work Completed Last Month:

  • Frame & Truss
  • Exterior Wrap

Work Planned This Month:

  • Roof
  • Windows
  • GIB Fix & Stop
  • Cladding

Estimated Settlement Date: March 2022

11 Townhouses

19 Karamu Street

Te Atatu Peninsula

Work Completed Last Month:

  • Frame & Truss
  • Exterior Wrap
  • Concrete Paths

Work Planned This Month:

  • Roof
  • Windows
  • Cladding

Estimated Settlement Date: March 2022

11 Townhouses

22 Yeovil Road

Te Atatu Peninsula

Work Completed Last Month:

  • Slab
  • Drains
  • Concrete Paths

Work Planned This Month:

  • Frame & Truss
  • Roof
  • Windows
  • Exterior Wrap

Estimated Settlement Date: March 2022

11 Townhouses

137 Tirimoana Road

Te Atatu South

Work Completed Last Month:

  • Excavation
  • Slab

Work Planned This Month:

  • Drains
  • Frame & Truss

Estimated Settlement Date: March 2022

11 Townhouses

10 Willcott Street

Mt Albert

Work Completed Last Month:

  • Planning & Consenting
  • Site Clearance

Work Planned This Month:

  • Excavation
  • Slab
  • Drains

Estimated Settlement Date: March 2022

13 Townhouses

87 Taikata Road

Te Atatu Peninsula

Work Completed Last Month:

  • Planning & Consenting

Work Planned This Month:

  • Site Clearance
  • Drains

Estimated Settlement Date: May 2022

10 Townhouses

59-61 Matipo Road

Te Atatu Peninsula

Work Completed Last Month:

  • Planning & Consenting

Work Planned This Month:

  • Planning & Consenting Continued
  • Site Clearance
  • Excavation
  • Drains

Estimated Settlement Date: May 2022

22 Townhouses

200 Carrington Road

Mt Albert

Work Completed Last Month:

  • Planning & Consenting

Work Planned This Month:

  • Planning & Consenting Continued
  • Site Clearance
  • Excavation

Estimated Settlement Date: June 2022

34 Townhouses

170 Don Buck Road

Massey

Work Completed Last Month:

  • Planning & Consenting

Work Planned This Month:

  • Planning & Consenting Continued

Estimated Settlement Date: September 2022

22 Townhouses

10-12 Fathom Place

Te Atatu Peninsula

Work Completed Last Month:

  • Planning & Consenting

Work Planned This Month:

  • Planning & Consenting Continued
  • Excavation

Estimated Settlement Date: September 2022, this has shifted due to delays with consenting at Auckland Council.

22 Townhouses

Got a Question?

Talk to a Client Consultant

Christchurch Build Updates

243 Kilmore Street

Central Christchurch

Work Completed Last Month:

  • Cladding
  • Landscaping

Work Planned This Month:

  • Internal Fit Off

Estimated Settlement Date: November 2021

6 Townhouses

232 Worcester Street

Central Christchurch

Work Completed Last Month:

  • Planning & Consenting
  • Site Clearance
  • Excavation
  • Slab
  • Drains
  • Frame & Truss
  • Roof
  • Windows
  • Exterior Wrap
  • GIB Fix & Stop
  • Internal Painting
  • Kitchen

Work Planned This Month:

  • Cladding
  • Landscaping
  • Concrete Paths
  • Internal Fit Off

Estimated Settlement Date: November 2021

11 Townhouses

35-41 Chester Street West

Central Christchurch

Work Completed Last Month:

  • Frame & Truss
  • Roof
  • Windows
  • Exterior Wrap

Work Planned This Month:

  • GIB Fix & Stop
  • Internal Painting
  • Cladding

Estimated Settlement Date: November 2021

15 Townhouses

320 Hereford Street

Central Christchurch

Work Completed Last Month:

  • Planning & Consenting
  • Site Clearance
  • Excavation
  • Slab
  • Drains

Work Planned This Month:

  • Frame & Truss
  • Roof
  • Windows

Estimated Settlement Date: December 2021

14 Townhouses

483-487 Selwyn Street

Central Christchurch

Work Completed Last Month:

  • Planning & Consenting
  • Site Clearance
  • Excavation
  • Slab
  • Drains

Work Planned This Month:

  • Frame & Truss
  • Roof

Estimated Settlement Date: December 2021

13 Townhouses

28 Aberdeen & 365 Madras Street

Central Christchurch

Work Completed Last Month:

  • Planning & Consenting
  • Site Clearance
  • Excavation

Work Planned This Month:

  • Slab
  • Drains

Estimated Settlement Date: March 2022

44 Townhouses

237 Lichfield Street

Central Christchurch

Work Completed Last Month:

  • Planning & Consenting
  • Site Clearance

Work Planned This Month:

  • Excavation

Estimated Settlement Date: April 2022

19 Townhouses

96 Tuam St

Central Christchurch

Work Completed Last Month:

  • Site Clearance
  • Excavation

Work Planned This Month:

  • Planning & Consenting Continued

Estimated Settlement Date: May 2022

26 Townhouses

169-171 St Asaph Street

Central Christchurch

Work Completed Last Month:

  • Planning & Consenting

Work Planned This Month:

  • Planning & Consenting Continued

Estimated Settlement Date: May 2022

27 Townhouses

322 Durham Street

Central Christchurch

Work Completed Last Month:

  • Planning & Consenting

Work Planned This Month:

  • Site Clearance

Estimated Settlement Date: May 2022

18 Townhouses

835 Colombo Street

Central Christchurch

Work Completed Last Month:

  • Planning & Consenting

Work Planned This Month:

  • Site Clearance
  • Excavation

Estimated Settlement Date: May 2022

12 Townhouses

338 Cashel Street

Central Christchurch

Work Completed Last Month:

  • Planning & Consenting

Work Planned This Month:

  • Site Clearance
  • Excavation

Estimated Settlement Date: May 2022

19 Townhouses

9 Spencer Street

Addington

Work Completed Last Month:

  • Planning & Consenting

Work Planned This Month:

  • Planning & Consenting Continued

Estimated Settlement Date: June 2022

16 Townhouses

240 St Asaph Street & 15 Southwark Street

Central Christchurch

Work Completed Last Month:

  • Planning & Consenting

Work Planned This Month:

  • Planning & Consenting Continued

Estimated Settlement Date: September 2022

27 Townhouses

76 Banks Ave

Dallington

Work Completed Last Month:

  • Planning & Consenting

Work Planned This Month:

  • Planning & Consenting Continued

Estimated Settlement Date: October 2022

49 Townhouses

Got a Question?

Talk to a Client Consultant

Wellington Build Updates

123 Cambridge Terrace

Lower Hutt

Work Completed Last Month:

  • Exterior Wrap
  • GIB Fix & Stop
  • Internal Painting
  • Cladding

Work Planned This Month:

  • Landscaping
  • Concrete Paths
  • Carparks
  • Kitchen
  • Internal Fit Off

Estimated Settlement Date: December 2021

11 Townhouses

318-324 Oxford Terrace

Lower Hutt

Work Completed Last Month:

  • Internal Painting
  • Cladding

Work Planned This Month:

  • Landscaping
  • Concrete Paths
  • Carparks
  • Kitchen
  • Internal Fit Off

Estimated Settlement Date: January 2022

28 Townhouses

4 Collingwood Street

Lower Hutt

Work Completed Last Month:

  • Roof
  • Windows
  • Exterior Wrap
  • GIB Fix & Stop

Work Planned This Month:

  • Internal Painting
  • Cladding
  • Landscaping
  • Kitchen
  • Internal Fit Off

Estimated Settlement Date: January 2022

11 Townhouses

14 Bauchop Road

Lower Hutt

Work Completed Last Month:

  • GIB Fix & Stop
  • Internal Painting

Work Planned This Month:

  • Cladding
  • Landscaping
  • Concrete Paths
  • Kitchen
  • Internal Fit Off

Estimated Settlement Date: January 2022

13 Townhouses

148 Riverside Drive

Lower Hutt

Work Completed Last Month:

  • Roof
  • Windows
  • Exterior Wrap

Work Planned This Month:

  • GIB Fix & Stop
  • Internal Painting
  • Cladding
  • Kitchen

Estimated Settlement Date: January 2022

11 Townhouses

10 Avery Grove

Lower Hutt

Work Completed Last Month:

  • GIB Fix & Stop
  • Internal Painting

Work Planned This Month:

  • Cladding
  • Landscaping
  • Kitchen
  • Internal Fit Off

Estimated Settlement Date: February 2022

14 Townhouses

11 Cressy Street

Lower Hutt

Work Completed Last Month:

  • GIB Fix & Stop

Work Planned This Month:

  • Internal Painting
  • Cladding
  • Landscaping
  • Kitchen
  • Internal Fit Off

Estimated Settlement Date: February 2022

8 Townhouses

17-19 Pearce Crescent

Lower Hutt

Work Completed Last Month:

  • Frame & Truss
  • Roof
  • Windows
  • Exterior Wrap

Work Planned This Month:

  • GIB Fix & Stop
  • Internal Painting
  • Cladding

Estimated Settlement Date: March 2022

12 Townhouses

182-183 Cambridge Terrace

Lower Hutt

Work Completed Last Month:

  • Slab
  • Drains
  • Frame & Truss
  • Roof
  • Windows

Work Planned This Month:

  • Exterior Wrap
  • GIB Fix & Stop
  • Internal Painting
  • Cladding

Estimated Settlement Date: May 2022

14 Townhouses

10-16 Biddle Crescent

Lower Hutt

Work Completed Last Month:

  • Excavation

Work Planned This Month:

  • Slab
  • Drains
  • Frame & Truss
  • Roof
  • Windows

Estimated Settlement Date: May 2022

30 Townhouses

5-7 Milne Crescent

Lower Hutt

Work Completed Last Month:

  • Excavation
  • Slab

Work Planned This Month:

  • Drains
  • Frame & Truss
  • Roof
  • Windows

Estimated Settlement Date: June 2022

16 Townhouses

1 Milne Crescent

Lower Hutt

Work Completed Last Month:

  • Planning & Consenting
  • Site Clearance
  • Excavation

Work Planned This Month:

  • Slab
  • Drains
  • Frame & Truss

Estimated Settlement Date: June 2022

17 Townhouses

5-11 Macky Street

Lower Hutt

Work Completed Last Month:

  • Planning & Consenting
  • Site Clearance

Work Planned This Month:

  • Excavation
  • Slab

Estimated Settlement Date: June 2022

24 Townhouses

39 Merton Street

Upper Hutt

Work Completed Last Month:

  • Planning & Consenting

Work Planned This Month:

  • Planning & Consenting Continued
  • Site Clearance
  • Excavation

Estimated Settlement Date: June 2022

18 Townhouses

4 Johnston Grove

Lower Hutt

Work Completed Last Month:

  • Planning & Consenting
  • Site Clearance

Work Planned This Month:

  • Slab
  • Drains

Estimated Settlement Date: July 2022

19 Townhouses

41 Collingwood Street

Lower Hutt

Work Completed Last Month:

  • Planning & Consenting

Work Planned This Month:

  • Site Clearance
  • Excavation

Estimated Settlement Date: September 2022

12 Townhouses