Build Updates

Check out this month’s build updates below.

Last updated 01/04/2021

Auckland
Christchurch
Wellington

Auckland Build Updates

21 Karamu Street

Te Atatū Peninsula

Landscaping complete. Final external and internal clean undertaken. Awaiting EACC, settlements due to commence April. Estimated settlement April 2021.

10 Townhouses

2 Jadewynn Drive

Massey

The roof install is complete. Windows, doors, cladding, and insulation to progress throughout April. Estimated settlement July 2021.

7 Townhouses

7 Flanshaw Road

Te Atatu South

Rear block: GIB and cladding install progressing. Front block: 1st-floor frames being stood, mid-floor to be constructed and 2nd-floor frames to be delivered the first week in April. Trusses to be stood early April. Estimated settlements July 2021

10 Townhouses

17 Lowtherhurst Road

Massey

The roof install is complete. Windows, doors, insulation, GIB, and cladding install to progress throughout April. Estimated settlement July 2021.

7 Townhouses

41 Kervil Avenue

Te Atatu Peninsula

Drainage, retaining and excavation works underway and progressing throughout April. Estimated settlement September 2021.

11 Townhouses

34 Sunnymead Road

Glen Innes

Public drainage works progressing throughout April, awaiting building consent. Estimated settlement September 2021.

10 Townhouses

32 Sunnymead Road

Glen Innes

Public drainage works progressing throughout April, awaiting building consent. Estimated settlement September 2021.

10 Townhouses

14 Wilsher Crescent

Henderson

Planning development and awaiting consent. Estimated settlement September 2021.

8 Townhouses

24 Yeovil Road

Te Atatu Peninsula

Site demolished and cleared, awaiting consents. Estimated settlement September/October 2021.

11 Townhouses

19 Karamu Street

Te Atatu Peninsula

Planning development and awaiting consent. Estimated settlement September/October 2021.

11 Townhouses

10 & 12 Wilsher Crescent

Henderson

Planning development and awaiting consent. Estimated settlement October 2021.

14 Townhouses

21 & 23 Titoki Street

Te Atatu Peninsula

Planning development and awaiting consent. Estimated settlement October 2021.

14 Townhouses

79 Taikata Road

Te Atatu Peninsula

Awaiting building consent. Drainage works commencing the first week of April. Estimated settlement October 2021.

11 Townhouses

22 Yeovil Road

Te Atatu Peninsula

Planning development and awaiting consent. Estimated settlement October 2021.

11 Townhouses

10 Yeovil Road

Te Atatu Peninsula

Site demolished and cleared, awaiting consent. Estimated settlement October 2021.

11 Townhouses

40 & 42 Kaikoura Street

Henderson

Planning development and awaiting consent. Estimated settlement October/November 2021.

15 Townhouses

10-12 Fathom Place

Te Atatu Peninsula

Planning development and awaiting consent. Estimated settlement November/December 2021.

22 Townhouses

137 Tirimoana Road

Te Atatu South

Planning development and awaiting consent. Estimated settlement TBC.

11 Townhouses

57 Taikata Road

Te Atatu Peninsula

Planning development and awaiting consent. Estimated settlement TBC.

10 Townhouses

59 Neil Avenue

Te Atatu Peninsula

Planning development and awaiting consent. Estimated settlement TBC.

11 Townhouses

137 View Road

Sunnyvale

Planning development and awaiting consent. Estimated settlement TBC.

8 Townhouses

81 Kervil Avenue

Te Atatu Peninsula

Planning development and awaiting consent. Estimated settlement TBC.

11 Townhouses

Christchurch Build Updates

29-31 Webb Street

Merivale

Project completed. Estimated settlement start of April 2021.

8 Townhouses

105 Purchas Street

Edgeware

The cladding install is being completed. Internal skirting and architraves underway inside. Estimated settlement start of May 2021.

19 Townhouses

64-66 Longfellow Street

Sydenham

Frames and roofs completed. Cladding to start being installed and carpark being prepped and poured. Estimated settlement start of June 2021.

9 Townhouses

241 Lincoln Road

Addington

Foundations now complete, with drainage work underway. Frames booked for delivery in the first week of April. Estimated settlement start of July 2021.

20 Townhouses

255 Gloucester Street

Central Christchurch

Foundation prep completed, concrete to be poured early April, then drainage work will start. Estimated settlement start of August 2021.

21 Townhouses

263 Gloucester Street

Central Christchurch

The site has been cleared and waiting for Building Consent to be issued. Once received, foundations will be starting in early April. Estimated settlement start of August 2021.

21 Townhouses

14-18 Nova Place and 243 Kilmore Street

Central Christchurch

Expecting Building Consent to be issued in early April. Then work on retaining walls and foundations will commence. Estimated settlement end of August 2021.

26 Townhouses

232 Worcester Street

Central Christchurch

Planning development and awaiting consent. Estimated settlement start of October 2021.

11 Townhouses

35-41 Chester Street West

Central Christchurch

Waiting on Building Consent to be issued. Estimated start date May 17th. Estimated settlement start of October 2021.

15 Townhouses

28 Aberdeen & 365 Madras Street

Central Christchurch

Asbestos and demo work to start 18th May 2021. Estimated settlement mid November 2021.

44 Townhouses

240 St Asaph Street & 15 Southwark Street

Central Christchurch

Planning development and working through the land settlement. Estimated settlement TBC.

27 Townhouses

76 Banks Ave

Dallington

Planning development and awaiting consent. Estimated settlement TBC.

49 Townhouses

483 & 487 Selwyn Street

Central Christchurch

Planning development and awaiting consent. Estimated settlement TBC.

13 Townhouses

Wellington Build Updates

27 Waiwhetu Road

Lower Hutt

Cladding and internal painting complete. Tiler and kitchen installs starting early April. Landscaping being prepped. Estimated settlement end of April 2021.

6 Townhouses

176 Cambridge Terrace

Lower Hutt

Cladding install complete. External landscaping and internal painting underway. Estimated settlement early May 2021.

7 Townhouses

97 Whites Lines East

Lower Hutt

External cladding installed and ready for painting. Internal linings starting in early April. Estimated settlement May 2021.

8 Townhouses

42 Cambridge Terrace

Lower Hutt

Internal linings are ready for install in the rear townhouses. Roof currently being installed on front block. Estimated settlement June 2021.

8 Townhouses

29-31 Waiwhetu Road

Lower Hutt

Foundations completed, ground floor frames are being stood. Estimated settlement July 2021.

14 Townhouses

318 – 320 Oxford Terrace

Lower Hutt

Block 1 concrete pour is underway. Block 2 is ready for concrete pour next week. Blocks 3+4 prepped and ready to pour following Block 2. Estimated settlement September 2021.

28 Townhouses

123 Cambridge Terrace

Lower Hutt

Excavations are currently underway. Estimated settlement October 2021.

11 Townhouses

4 Collingwood Street

Lower Hutt

Planning development and awaiting consent. Estimated settlement TBC.

11 Townhouses

148 Riverside Drive

Lower Hutt

Planning development and awaiting consent. Estimated settlement TBC.

11 Townhouses

11 Cressy Street

Lower Hutt

Planning development and awaiting consent. Estimated settlement TBC.

8 Townhouses

14 Bauchop Road

Lower Hutt

Planning development and awaiting consent. Estimated settlement TBC.

13 Townhouses

10 Avery Grove

Lower Hutt

Planning development and awaiting consent. Estimated settlement TBC.

14 Townhouses

17-19 Pearce Crescent

Lower Hutt

Planning development and awaiting consent. Estimated settlement TBC.

11 Townhouses

4 Johnston Grove

Lower Hutt

Planning development and awaiting consent. Estimated settlement TBC.

19 Townhouses