Check out this month’s build updates below.
Last updated 07/12/2020
Job Completed, Awaiting Titles from LINZ and COC from Council, estimated settlement week of 14th September.
Code Compliance Certificate has been approved and now are just awaiting on titles. We expect settlements to start from December 10th.
Code Compliance Certificate has been approved and now are just awaiting on titles. We expect settlements to start from December 10th.
Landscaping completed, awaiting Code Compliance Certificate to issue. Estimated settlement end of October.
Landscaping completed, awaiting Code Compliance Certificate to issue. Estimated settlement end of October.
The project is completed. Due to storm water connection re-route delays, settlements are now expected in mid-February.
The project is completed. Due to storm water connection re-route delays, settlements are now expected in mid-February.
The project is completed, settlements due to start early February.
The project is completed, settlements due to start early February.
The project completed, settlements are due to begin mid-February.
The project completed, settlements are due to begin mid-February.
Final inspections passed. Estimated settlement late February 2021.
Final inspections passed. Estimated settlement late February 2021.
Carpet and second fix being installed. Final inspections 25th of January, estimated settlements late march.
Carpet and second fix being installed. Final inspections 25th of January, estimated settlements late march.
Building consent issued, foundations have started, pre-nail framing is in production. Estimated settlement July 2021.
Building consent issued, foundations have started, pre-nail framing is in production. Estimated settlement July 2021.
Cladding is underway, and internal painting and tiling complete. Slight delay in EACC application due to water mains connection re-routing. Estimated settlement in march 2021.
Cladding is underway, and internal painting and tiling complete. Slight delay in EACC application due to water mains connection re-routing. Estimated settlement in march 2021.
Drainage complete, pads ready for foundations to start on Monday- Settlements June 2021.
Drainage complete, pads ready for foundations to start on Monday- Settlements June 2021.
Drainage complete next week, building consent issued. Foundations starting on the 28th of January 2021.
Drainage complete next week, building consent issued. Foundations starting on the 28th of January 2021.
Consenting underway with construction commencing Jan 2021. Estimated settlement July 2021.
Consenting underway with construction commencing Jan 2021. Estimated settlement July 2021.
Consenting underway with construction commencing Feb 2021. Estimated settlement August 2021.
Consenting underway with construction commencing Feb 2021. Estimated settlement August 2021.
Consenting underway with construction commencing Feb 2021. Estimated settlement August 2021.
Consenting underway with construction commencing Feb 2021. Estimated settlement August 2021.
Consenting underway with demolition due to commence in February. Completion estimated for September 2021.
Consenting underway with demolition due to commence in February. Completion estimated for September 2021.
Consenting underway with demolition due to commence in February. Completion estimated for September 2021.
Consenting underway with demolition due to commence in February. Completion estimated for September 2021.
Consenting underway with demolition due to commence in February. Completion estimated for September 2021.
Consenting underway with demolition due to commence in February. Completion estimated for September 2021.
Consenting underway with demolition due to commence in March. Completion estimated for September 2021.
Consenting underway with demolition due to commence in March. Completion estimated for September 2021.
Consenting underway with demolition due to commence in March. Completion estimated for September 2021.
Consenting underway with demolition due to commence in March. Completion estimated for September 2021.
Settlements almost completed. Warranties and Property Manager Information Booklets were placed in each Townhouse.
Settlements almost completed. Warranties and Property Manager Information Booklets were placed in each Townhouse.
Settlements almost completed. Warranties and Maintenance Booklets were placed in each Townhouse.
Settlements almost completed. Warranties and Maintenance Booklets were placed in each Townhouse.
Settlements almost completed. Warranties and Maintenance Booklets were placed in each Townhouse.
Settlements almost completed. Warranties and Maintenance Booklets were placed in each Townhouse.
Final stages of fencing and landscaping – looking like settlements will be early February 21.
Final stages of fencing and landscaping – looking like settlements will be early February 21.
Frames onsite.
Frames onsite.
Final stages of landscaping and fencing–settlements last week of January.
Final stages of landscaping and fencing–settlements last week of January.
Piling contractor onsite installing piles for foundations.
Piling contractor onsite installing piles for foundations.
Slabs are being started on Monday 18th.
Kerbs and driveway installed.
Slabs are being started on Monday 18th.
Kerbs and driveway installed.
Starting asbestos removal and demo start of Feb.
Starting asbestos removal and demo start of Feb .
Starting asbestos removal and demo start of Feb.
Starting asbestos removal and demo start of Feb.
Starting start of March waiting on BC site cleared ready for retaining walls and earthworks start of March.
Starting start of March waiting on BC site cleared ready for retaining walls and earthworks start of March.
Starting earthworks start of March settlements looking like August.
Starting earthworks start of March settlements looking like August.
Starting earthworks start of March settlements looking like August.
Starting earthworks start of March settlements looking like August.
Consenting underway with commencement March. Estimated settlement October 2021.
Consenting underway with commencement March. Estimated settlement October 2021.
Estimated completion in 2021.
Estimated completion in 2021.
All works nearly completed. Final touches for landscaping to be complete, kitchen bench tops and final fit off for the kitchen to be completed. Estimated settlement early February 2021.
All works nearly completed. Final touches for landscaping to be complete, kitchen bench tops and final fit off for the kitchen to be completed. Estimated settlement early February 2021.
Frames have been completed with ecoply and tape. The roof is currently being installed. Sub trades are starting on the insides. Estimated settlement early April 2021.
Frames have been completed with ecoply and tape. The roof is currently being installed. Sub trades are starting on the insides. Estimated settlement early April 2021.
All frames stood with eco ply being installed. Roof is about to start and windows are being delivered. Estimated settlement mid April 2021.
All frames stood with eco ply being installed. Roof is about to start and windows are being delivered. Estimated settlement mid April 2021.
Ground floor erected with mid floor being installed. Drainage and services being run in the ground. Estimated settlement mid May 2021.
Ground floor erected with mid floor being installed. Drainage and services being run in the ground. Estimated settlement mid May 2021.
Foundations are being prepared with boxing and reinforcement. Estimated settlements mid June 2021.
Foundations are being prepared with boxing and reinforcement. Estimated settlements mid June 2021.
Foundations are being marked out, boundary fences starting to be installed and surveyor marking out the gridlines. Estimated settlements September 2021.
Foundations are being marked out, boundary fences starting to be installed and surveyor marking out the gridlines. Estimated settlements September 2021.
Foundations starting to be dug out. Estimated settlement mid July 2021.
Foundations starting to be dug out. Estimated settlement mid July 2021.
Awaiting consent. Estimated settlement late December 2021.
Awaiting consent. Estimated settlement late December 2021.
Consenting underway. Estimated settlement late December 2021.
Consenting underway. Estimated settlement late December 2021.
Demolition and asbestos removal starting. Estimated settlement late December 2021.
Demolition and asbestos removal starting. Estimated settlement late December 2021.
Hands-on advice for homeowners and investors.
Your one-stop handbook by the Managing Directors of Williams Corporation, Matthew Horncastle and Blair Chappell. Join thousands of others by downloading our FREE handbook to Buying Property in New Zealand.
Subscribe to our newsletter for our latest developments, industry updates and Williams Corporation news.
[instagram-feed]