Build Updates.

Check out this month’s build updates below.

Last updated 14/10/2020

Auckland Build Updates.

previous arrow
next arrow
Slider

52 Vodanovich Road
7 Townhouses

Job Completed, Awaiting Titles from LINZ and COC from Council, estimated settlement week of 14th September.

102 Millbrook Road
9 Townhouses

Landscaping almost complete, awaiting Code Compliance Certificate to issue. Estimated settlement end of October.

102 Millbrook Road – 9 Townhouses

Landscaping almost complete, awaiting Code Compliance Certificate to issue. Estimated settlement end of October.

80 Awaroa Road
6 Townhouses

Landscaping completed, awaiting Code Compliance Certificate to issue. Settlement in November.

80 Awaroa Road – 6 Townhouses

Landscaping completed, awaiting Code Compliance Certificate to issue. Settlement in November.

86 Vodanovich
6 Townhouses

Landscaping completed, awaiting Code Compliance Certificate to issue. Estimated settlement end of October.

86 Vodanovich – 6 Townhouses

Landscaping completed, awaiting Code Compliance Certificate to issue. Estimated settlement end of October.

8 Yeovil Road
11 Townhouses

Cladding has commenced, final windows going in and insulation being installed. Estimated settlement January 2021.

8 Yeovil Road – 11 Townhouses

Cladding has commenced, final windows going in and insulation being installed. Estimated settlement January 2021.

24 Kelwyn Road
7 Townhouses

Framing completed, roof on and driveway poured. Estimated settlement January 2021.

24 Kelwyn Road – 7 Townhouses

Framing completed, roof on and driveway poured. Estimated settlement January 2021.

22 Denver Avenue
9 Townhouses

Framing completed, roof is on, paths and carpark to be poured early next week. Estimated settlement February 2021.

22 Denver Avenue – 9 Townhouses

Framing completed, roof is on, paths and carpark to be poured early next week. Estimated settlement February 2021.

6 St Leonards Road
8 Townhouses

Framing delivered, trusses arriving early next week and carpark preparation underway. Estimated settlement February 2021.

6 St Leonards Road – 8 Townhouses

Framing delivered, trusses arriving early next week and carpark preparation underway. Estimated settlement February 2021.

87 Beach Road
8 Townhouses

The slab is down and framing going up. Estimated settlement March 2021.

87 Beach Road – 8 Townhouses

The slab is down and framing going up. Estimated settlement March 2021.

2 Jadewynn Drive
7 Townhouses

Awaiting building consent to issue. Estimated settlement May 2021.

2 Jadewynn Drive – 7 Townhouses

Awaiting building consent to issue. Estimated settlement May 2021.

21 Karamu Street
10 Townhouses

Slab boxing underway, slab poured, framing arriving this week. Estimated settlement May 2021.

21 Karamu Street – 10 Townhouses

Slab boxing underway, slab poured, framing arriving this week. Estimated settlement May 2021.

7 Flanshaw Road
10 Townhouses

Demolition completed with construction commencing Jan 2021. Estimated settlements May 2021.

7 Flanshaw Road – 10 Townhouses

Demolition completed with construction commencing Jan 2021. Estimated settlements May 2021.

17 Lowtherhurst Road
7 Townhouses

Consenting underway with construction commencing Jan 2021. Estimated settlement July 2021.

17 Lowtherhurst Road – 7 Townhouses

Consenting underway with construction commencing Jan 2021. Estimated settlement July 2021.

21 Titoki Street
14 Townhouses

Consenting underway with construction commencing Jan 2021. Estimated settlement July 2021.

21 Titoki Street – 14 Townhouses

Consenting underway with construction commencing Jan 2021. Estimated settlement July 2021.

41 Kervil Avenue
11 Townhouses

Consenting underway with construction commencing Feb 2021. Estimated settlement August 2021.

41 Kervil Avenue – 11 Townhouses

Consenting underway with construction commencing Feb 2021. Estimated settlement August 2021.

40 Kaikoura Street
14 Townhouses

Consenting underway with construction commencing Feb 2021. Estimated settlement August 2021.

40 Kaikoura Street – 14 Townhouses

Consenting underway with construction commencing Feb 2021. Estimated settlement August 2021.

34 Sunnymead Road
10 Townhouses

Consenting underway with demolition due to commence in February. Completion estimated for September 2021.

34 Sunnymead Road – 10 Townhouses

Consenting underway with demolition due to commence in February. Completion estimated for September 2021.

32 Sunnymead Road
10 Townhouses

Consenting underway with demolition due to commence in February. Completion estimated for September 2021.

32 Sunnymead Road – 10 Townhouses

Consenting underway with demolition due to commence in February. Completion estimated for September 2021.

Christchurch Build Updates.

201 – 205 Salisbury Street
28 Townhouses

Scaffolding coming down and landscaping commenced. Settlements due mid-November.

201 – 205 Salisbury Street – 28 Townhouses

Scaffolding coming down and landscaping commenced. Settlements due mid-November.

41 Gracefield Avenue
6 Townhouses

Exterior cladding almost complete and schist being installed. Estimated settlements mid-November.

41 Gracefield Avenue – 6 Townhouses

Exterior cladding almost complete and schist being installed. Estimated settlements mid-November.

159 Deans Avenue, 8 Riccarton Road, 8 Darvel Street
43 Townhouses

Scaffolding down on Stage 1, scaffolding coming down on Stages 2 and 3 in the next 2weeks and landscaping commencing over all Stages. Estimated settlements end of November.

159 Deans Avenue, 8 Riccarton Road, 8 Darvel Street – 43 Townhouses

Scaffolding down on Stage 1, scaffolding coming down on Stages 2 and 3 in the next 2weeks and landscaping commencing over all Stages. Estimated settlements end of November.

131 Merivale Lane
18 Townhouses

Roof going on, cladding commenced and carpark being prepared. Estimated settlement January 2021.

131 Merivale Lane – 18 Townhouses

Roof going on, cladding commenced and carpark being prepared. Estimated settlement January 2021.

88 Peverel Street
7 Townhouses

Final Stages of consenting, construction starting Mid September, estimated settlements March 2021.

88 Peverel Street – 7 Townhouses

Final Stages of consenting, construction starting Mid September, estimated settlements March 2021.

62 Elizabeth Street
7 Townhouses

Frames being delivered this week. Estimated settlement May 2021.

62 Elizabeth Street – 7 Townhouses

Frames being delivered this week. Estimated settlement May 2021.

105 Purchas Street
22 Townhouses

Awaiting consent with construction commencing in November. Estimated settlement June 2021.

105 Purchas Street – 22 Townhouses

Awaiting consent with construction commencing in November. Estimated settlement June 2021.

29-31 Webb Street
8 Townhouses

Commenced site scrap. Estimated settlement May 2021.

29-31 Webb Street – 8 Townhouses

Commenced site scrap. Estimated settlement May 2021.

241 Lincoln Road
20 Townhouses

Awaiting consent with commencement January 2021. Estimated settlement August 2021.

241 Lincoln Road – 20 Townhouses

Awaiting consent with commencement January 2021. Estimated settlement August 2021.

64-66 Longfellow Street
9 Townhouses

Awaiting consent with commencement end of January 2021. Estimated settlement August 2021.

64-66 Longfellow Street – 9 Townhouses

Awaiting consent with commencement end of January 2021. Estimated settlement August 2021.

14-18 Nova Place and 243 Kilmore Street
26 Townhouses

Consenting underway with commencement mid-November. Estimated settlement July 2021.

14-18 Nova Place and 243 Kilmore Street – 26 Townhouses

Consenting underway with commencement mid-November. Estimated settlement July 2021.

255 Gloucester Street
21 Townhouses

Consenting underway with commencement February. Estimated settlement September 2021.

255 Gloucester Street – 21 Townhouses

Consenting underway with commencement February. Estimated settlement September 2021.

263 Gloucester Street
21 Townhouses

Consenting underway with commencement February. Estimated settlement September 2021.

263 Gloucester Street – 21 Townhouses

Consenting underway with commencement February. Estimated settlement September 2021.

Wellington Build Updates.

36 Mitchell Street
7 Townhouses

Cladding commenced, windows and doors are in and insulation is completed. Estimated settlement mid-Dec 2020.

36 Mitchell Street – 7 Townhouses

Cladding commenced, windows and doors are in and insulation is completed. Estimated settlement mid-Dec 2020.

27 Waiwhetu Road
6 Townhouses

Ground preparation, slab boxing commencing with the concrete pour due in 2 weeks. Estimated settlement March 2021.

27 Waiwhetu Road – 6 Townhouses

Ground preparation, slab boxing commencing with the concrete pour due in 2 weeks. Estimated settlement March 2021.

176 Cambridge Terrace
7 Townhouses

Earthworks completed, slab boxing commencing. Estimated settlement March 2021.

176 Cambridge Terrace – 7 Townhouses

Earthworks completed, slab boxing commencing. Estimated settlement March 2021.

97 Whites Lines East
8 Townhouses

Demolition completed and boundary fencing underway. Estimated settlement April 2021.

97 Whites Lines East – 8 Townhouses

Demolition completed and boundary fencing underway. Estimated settlement April 2021.

42 Cambridge Terrace
7 Townhouses

Awaiting consent, estimated start date of December. Estimated settlements June 2021.

42 Cambridge Terrace – 7 Townhouses

Awaiting consent, estimated start date of December. Estimated settlements June 2021.

318 – 320 Oxford Terrace
28 Townhouses

Awaiting consent, estimated start date of December. Estimated settlements August 2021.

318 – 320 Oxford Terrace – 28 Townhouses

Awaiting consent, estimated start date of December. Estimated settlements August 2021.

29-31 Waiwhetu Road
14 Townhouses

Awaiting consent, estimated start date of December. Estimated settlement August 2021.

29-31 Waiwhetu Road – 14 Townhouses

Awaiting consent, estimated start date of December. Estimated settlement August 2021.

148 Riverside Drive
11 Townhouses

Consenting underway and gas services ordered. Estimated settlement late 2021.

148 Riverside Drive – 11 Townhouses

Consenting underway and gas services ordered. Estimated settlement late 2021.

Download your FREE Property Handbook.

Hands-on advice for homeowners and investors.

Your one-stop handbook by the Managing Directors of Williams Corporation, Matthew Horncastle and Blair Chappell. Join thousands of others by downloading our FREE handbook to Buying Property in New Zealand.

Online Property Handbook

Subscribe.

Subscribe to our newsletter for our latest developments, industry updates and Williams Corporation news.

Follow Us On Instagram.

[instagram-feed]