Build Updates

Check out this month’s build updates below.

Last updated 01/06/2021

Auckland
Christchurch
Wellington
Talk to Us

Auckland Build Updates

2 Jadewynn Drive

Massey

Interior and exterior painting now complete. Kitchen install and retaining extension works progressing well. Carpark prep for pour underway. Estimated settlement July 2021.

7 Townhouses

17 Lowtherhurst Road

Massey

Landscaping progressing, electrical and plumbing fit-off underway. Carpet being installed. Scheduled for completion next month. Estimated settlement July 2021.

7 Townhouses

7 Flanshaw Road

Te Atatu South

Rear block: Plumbing and electrical fit-off progressing. Carpet and kitchen installation complete. Landscaping progressing on-site. Front block: Interior painting progressing, kitchens to be installed next week. Estimated settlement August 2021.

10 Townhouses

41 Kervil Avenue

Te Atatu Peninsula

All frames and trusses have been stood, roof scheduled for this week. Windows and doors being installed, retaining progressing at site frontage along with first fix plumbing and rondo install. Estimated settlement November 2021.

11 Townhouses

34 Sunnymead Road

Glen Innes

Public drainage works complete outside boundary, progressing with drainage and retaining inside boundary. Estimated settlement December 2021.

10 Townhouses

32 Sunnymead Road

Glen Innes

Public drainage works complete outside boundary, progressing with drainage and retaining inside boundary. Estimated settlement December 2021.

10 Townhouses

14 Wilsher Crescent

Henderson

Building Consent received, retaining and public drainage works progressing on site inside the boundary. Estimated settlement December 2021.

8 Townhouses

79 Taikata Road

Te Atatu Peninsula

Raft foundations and excavation works progressing. Retaining and drainage works due to commence this week. Estimated settlement December 2021.

11 Townhouses

21 - 23 Titoki Street

Te Atatu Peninsula

Retaining and public drainage works progressing inside the site. Public drainage complete outside the boundary. Estimated settlement December 2021.

14 Townhouses

57 Taikata Road

Te Atatu Peninsula

Drainage and foundations complete. Slab prep and boxing due to commence this week. Frames in 3 weeks. Estimated settlement December 2021.

10 Townhouses

137 View Road

Sunnyvale

Consents have been received, and public drainage work is complete inside the boundary. Retaining work about to commence, awaiting material supply. Estimated settlement December 2021.

8 Townhouses

10 Yeovil Road

Te Atatu Peninsula

Public drainage and excavation complete inside boundary. Consents now received and retaining works scheduled to start inside site. Estimated settlement December 2021.

11 Townhouses

59 Neil Avenue

Te Atatu Peninsula

Consents received, public drainage progressing inside the site, services (Chorus, Water & Power) have been laid. Excavation scheduled to commence. Estimated settlement December 2021.

11 Townhouses

40 - 42 Kaikoura Street

Henderson

Slab prepped and boxed, scheduled for concrete pour. Ground floor frames booked for delivery next week. Estimated settlement December 2021.

15 Townhouses

24 Yeovil Road

Te Atatu Peninsula

Demolition of the existing site is complete. Awaiting approval of consents from Auckland Council to progress with further works. Estimated settlement January 2022.

11 Townhouses

19 Karamu Street

Te Atatu Peninsula

Existing house has been demolished, and site cleared. Awaiting consents from Auckland Council. Estimated settlement January 2022.

11 Townhouses

10 - 12 Wilsher Crescent

Henderson

Building Consent received, retaining and public drainage works progressing on site inside the boundary. Estimated settlement January 2022.

14 Townhouses

81 Kervil Avenue

Te Atatu Peninsula

The existing house has been demolished, and site cleared. Awaiting remaining consents from Auckland Council. Estimated settlement January 2022.

11 Townhouses

22 Yeovil Road

Te Atatu Peninsula

Demolition of the existing site is complete. Awaiting approval of consents from Auckland Council to progress with further works. Estimated settlement January 2022.

11 Townhouses

10 - 12 Fathom Place

Te Atatu Peninsula

Demolition underway on site, awaiting consents to commence further works. Estimated settlement February 2022.

22 Townhouses

137 Tirimoana Road

Te Atatu South

Design and planning complete, awaiting consents from Auckland Council. Estimated settlement March 2022.

11 Townhouses

10 Willcott Street

Mt Albert

Design and planning complete, awaiting consents and land settlement. Estimated settlement April 2022.

13 Townhouses

87 Taikata Road

Te Atatu Peninsula

Planning development and awaiting consent. Estimated settlement May 2022.

10 Townhouses

59 - 61 Matipo Road

Te Atatu Peninsula

Planning development and awaiting consent. Estimated settlement May 2022.

22 Townhouses

200 Carrington Road

Mt Albert

Planning development and awaiting consent. Estimated settlement July 2022.

34 Townhouses

Got a Question?

Talk to a Client Consultant

Christchurch Build Updates

241 Lincoln Road

Addington

Scaffold coming down on the back units and internal painting underway. Estimated settlement June 2021.

20 Townhouses

255 Gloucester Street

Central Christchurch

Roof has been completed. Gib and cladding install is currently underway. Estimated settlement July 2021.

21 Townhouses

263 Gloucester Street

Central Christchurch

Frames and trusses have been installed. Roof is currently going on. Estimated settlement August 2021.

21 Townhouses

14 - 18 Nova Place and 243 Kilmore Street

Central Christchurch

Foundations have been completed and currently have frames on-site being stood. Estimated settlement August 2021.

26 Townhouses

105 Purchas Street

Edgeware

Stage 2 - Waiting on Cellphone tower to be removed on 21st July. Estimated settlement November 2021.

3 Townhouses

35 - 41 Chester Street West

Central Christchurch

Site has been cleared. Currently waiting on Building Consent to be issued. Estimated settlement November 2021.

15 Townhouses

28 Aberdeen & 365 Madras Street

Central Christchurch

The demolition of the existing building is currently underway. Estimated settlement December 2021.

44 Townhouses

232 Worcester Street

Central Christchurch

Planning development and awaiting consent. Estimated settlement November 2021.

11 Townhouses

483 & 487 Selwyn Street

Central Christchurch

Planning development and awaiting consent. Estimated settlement February 2022.

13 Townhouses

96 Tuam St

Central Christchurch

Planning development and awaiting consent. Estimated settlement February 2022.

26 Townhouses

76 Banks Ave

Dallington

Planning development and awaiting consent. Estimated settlement April 2022.

49 Townhouses

240 St Asaph Street & 15 Southwark Street

Central Christchurch

Planning development and working through the land settlement. Estimated settlement September 2022.

27 Townhouses

Got a Question?

Talk to a Client Consultant

Wellington Build Updates

97 Whites Lines East

Lower Hutt

Internal painting is currently being completed. Work starting to install kitchens, appliances and final fit off, along with exterior paths and landscaping. Estimated settlement August 2021.

8 Townhouses

29 - 31 Waiwhetu Road

Lower Hutt

Interior work is underway, with the installation of GIB and insulation. Cladding is also being installed on the exterior. Estimated settlement August 2021.

14 Townhouses

42 Cambridge Terrace

Lower Hutt

Exterior cladding is nearly complete. Internal works are progressing, with GIB installed, plaster and paint underway in the rear blocks. Once the scaffolding comes down, we will start landscaping and finishing work. Estimated settlement July 2021.

8 Townhouses

123 Cambridge Terrace

Lower Hutt

All slabs are now complete, awaiting delivery of frames to commencing standing and installing roof. Estimated settlement November 2021.

11 Townhouses

318 - 324 Oxford Terrace

Lower Hutt

Blocks 1-3: Trusses are installed, roof and ecoply going on to make the project watertight, with cladding also to be installed. Block 4: Waiting for a concrete pour on slabs, before aiming to catch up with the rest of the project. Estimated settlement December 2021.

28 Townhouses

4 Collingwood Street

Lower Hutt

Currently have one slab completed with concrete. Work to complete remaining slabs is underway, before standing ground/first floor frames and trusses. Estimated settlement December 2021.

11 Townhouses

14 Bauchop Road

Lower Hutt

Currently going through the install of the foundations. Will then be commencing with install of ground and first floor frames, and trusses. Estimated settlement December 2021.

13 Townhouses

148 Riverside Drive

Lower Hutt

Site excavation has been completed, piles are installed and awaiting the installation of the floor and slab for drainage to start. Estimated settlement December 2021.

11 Townhouses

10 Avery Grove

Lower Hutt

Currently completing foundation and drainage work. All piles have been installed, and awaiting concrete pour before the arrival of frames. Estimated settlement January 2022.

14 Townhouses

11 Cressy Street

Lower Hutt

Currently having asbestos removed from the existing home before demolition will take place. We will then be getting earthworks underway. Estimated settlement January 2022.

8 Townhouses

17 - 19 Pearce Crescent

Lower Hutt

Planning development and awaiting consent. Estimated settlement February 2022.

11 Townhouses

182 - 183 Cambridge Terrace

Lower Hutt

Planning development and awaiting consent. Estimated settlement April 2022.

14 Townhouses

10 - 16 Biddle Crescent

Lower Hutt

Planning development and awaiting consent. Estimated settlement April 2022.

30 Townhouses

4 Johnston Grove

Lower Hutt

Planning development and awaiting consent. Estimated settlement July 2022.

19 Townhouses

Talk to Us

Whether you’re a first time home buyer, investor or someone that’s interested in growing their portfolio, we have properties available now.

Talk to a Client Consultant